Description of Actual Services Provided by Staff of this Firm in the Assignment:
Scope of Services included –
§ Collection of necessary information and relevant data for preparing the Initial Environmental Examination (IEE) and Environmental & Social Impact Assessment (ESIA) Reports for 218.6kW Solar Photovoltaic Based Mini Grid Power Plant.
§ Collection of primary data, including extrapolation environmental features on proposed project design, tree inventories, location and measurement of socio-cultural features adjoining the proposed project area.
§ Collection of the secondary data on macro-environmental setting, such as, climate (temperature, rainfall, humidity, & wind speed), physiography, geology etc. from secondary sources.
§ Review of the environmental legislation, regulatory policy & guidelines, and considerations relating to the implementation of the project.
§ Review of the policy, legal and administrative framework for ESIA process.
§ Carry out the environmental and social impact assessment up to 1km area on each side of the project.
§ Establish the environmental and social baseline conditions of the project.
§ Assessment of the baseline environmental and social condition through field surveys and investigation (sampling & testing).
§ Impacts assessment of ecologically sensitive areas (e.g. wildlife sanctuaries, biosphere reserve, and protected places).
§ Environmental quality assessment of terrestrial and aquatic ecology, soil quality (parameters – oil & grease, arsenic), surface water quality (parameters – pH, TDS, DO, BOD, COD), groundwater quality (parameters – pH, Arsenic, TDS, Alkalinity, Fe, Chloride), air quality (parameters – SPM, Sox, NOx, CO, PM10, PM2.5), and noise level to prepare a baseline database.
§ Assess the existing physical environment, biological environment, and socio-economic environment.
§ Physical environment covered different physical natural features and included major parameters & factors, such as, climate (temperature, rainfall, humidity, wind speed, sunshine, & cloud coverage), ambient air quality, noise level, physiography, topography, geology & hydrology, water resources (surface & ground water), soil quality, agro-ecological zones (soil condition, & floodplain), seismicity, etc.
§ Biological environment covered factors related to life and included major features, such as, bio-ecological zones (major rivers), ecosystem, flora & fauna, protected areas & red book species, etc.
§ Socio-economic environment covered anthropological factors, such as, demography, age, sex/gender, household, nutrition, religion, ethnicity, land use ownership, cropping pattern, occupational pattern, livelihood, income, infrastructure, settlement plan & housing, transport & communication, sources of drinking water, sanitation facility, poverty, health, recreational activities, archaeological & cultural heritage, climate change & natural disaster, environmental & social hotspot, etc.
§ Prepare socio-economic profile and impact on the community.
§ Identification and assessment of potential impacts on the natural and human environment in the project area during pre-construction; construction and post-construction phase of the project.
§ Identification of mitigation measures for minimizing the effect of the negative impacts and enhancement measures for increasing the benefits of the positive impacts.
§ Organize public consultation to explain the local environmental & social conditions and pertinent impacts.
§ Preparation of the IEE Report, in compliance with the guidelines of the Department of Environment (DOE) of the Government of Bangladesh, JICA Guidelines for Loan Aid (Japan Bank for International Cooperation Guidelines for Confirmation of Environmental and Social Considerations, April 2010) and World Bank OP 4.01 (Environmental Assessment) guidelines.
§ Preparation of the TOR (Terms of Reference) for site clearance by the DOE.
§ Preparation of the EIA Report, including Social Impact Assessment (SIA), Environmental Management Plan (EMP) and Environmental Monitoring Plan, along with the budgetary cost estimates for the proposed mitigation measures and monitoring plan, in compliance with the DOE guidelines, JICA Guidelines for Loan Aid (Japan Bank for International Cooperation Guidelines for Confirmation of Environmental and Social Considerations, April 2010) and World Bank OP 4.01 (Environmental Assessment) guidelines.
§ Assist the Client in coordination and liaison with the DOE to organize presentation and facilitate the process of EIA approval and thereby issuance of Environmental Clearance Certificate (ECC) for the proposed solar power plant.
§ Successfully Received Site Clearance (SC) and Environmental Clearance Certificate (ECC) from Department of Environment (DoE) and approval from IDCOL. |